The activities to perform, their durations, and the precedence constraints between those activities are identical to those presented earlier, as shown in Table 3.1.
In addition, we have one worker who is required to perform all the activities. Because this worker can only perform one task at a time, we cannot schedule two activities at the same time, as we could in Example 1.