Once again, our example is based on the house building problem, with the goal of scheduling the tasks to finish the entire house as quickly as possible. It still consists of ten activities, but there is now an additional worker, identical in capability to the first worker.
As before, solving the problem consists of determining the earliest possible end time for the project. However, instead of a unary resource, we have a discrete resource with a capacity of 2.