In this example we have again four workers who are required to build five houses. However, instead of one worker who performs masonry
and another who performs plumbing
, we have two workers who are equally capable of performing the masonry
and plumbing
, and either of which can be selected to perform the activity.
The five houses have the three designs, and the corresponding activity durations, shown in Table 5.1 in Adding Transition Times. There are time constraints on the third and fourth houses that state that work on those houses cannot be started before day 5 and must be finished by day 57.
Once again, our objective is to minimize the makespan of the problem.